What's the most expensive part of a bathroom renovation?

Short answer

Labour — and within labour, tiling. A fully tiled south London bathroom carries £950–£1,500 of tiling labour alone, and moving soil pipes or upgrading old plumbing adds fast. The suite people budget hardest for is usually the smallest line on the invoice.

A typical full renovation invoice splits roughly: a third on plumbing and electrics (first fix, valve, certification), a third on tiling and waterproofing, and the rest across strip-out, flooring, fit-out and making good. The £700 suite from the warehouse and the £2,200 showroom suite sit in bathrooms whose totals differ far less than that gap suggests, because everything around them costs the same.

The two lines that blow budgets: moving the WC (the soil pipe is the least movable object in the house, and every metre of new run needs fall, support and boxing), and floor-to-ceiling tiling on all four walls, which roughly doubles the tiling labour versus wet-walls-only. Both are worth doing when the design earns them — they are just the honest place to look first when a quote needs trimming.

The corollary: the cheap-looking quote has usually trimmed the invisible third. If a quote is £2,000 under the others, the missing money is nearly always in tanking, first-fix, or certification — the parts you cannot see at handover and meet again in eighteen months.

Useful next steps
Related questions

More in costs & budgets, or browse all 38 questions on the FAQ index.

Price your project

Two quick steps. We reply within one working day.

No account, no obligation. We only use this to prepare your quote.

Ready to price your bathroom?

Tell us the room and the rough plan — we reply within one working day with an honest cost bracket, then a free home survey and a fixed written quote.

Start your quote 020 3051 9155